Salisbury braces for noise, hassle from beach project

SALISBURY — With the pumping of tons of sand onto Salisbury Beach poised to begin perhaps as early as today, Town Manager Neil Harrington warned residents that the operation could cause significant disruptions, if only for a few days.

Under contract with the U.S. Army Corps of Engineers, Great Lakes Dredge & Dock Co. of Oak Brook, Ill., will dredge the Merrimack River channel and deposit the sand directly onto beaches here and on Plum Island.

In addition to clearing the channel for marine traffic, the $5.5 million project is intended to replenish some badly eroded stretches of shoreline in both locations.

"The work in Salisbury will be done around the clock for four days straight, pumping 40,000 cubic yards of sand onto the beach," Harrington said in his regular report to the Board of Selectmen Monday night. "We will be asking the public to be understanding of the round-the-clock schedule for the dredging, as the contractor is attempting to get as much sand onto the beaches in the least amount of time."

People living near the work site can probably expect to lose some sleep.

Harrington said there will be inconvenience caused by lights and noise.

A project description distributed by the Army Corps also notes that the onshore equipment have backup alarms, "which for obvious safety reasons cannot be turned off."

There were three pieces of large earth-moving equipment — bulldozers and front-end loaders — on the beach as of yesterday and they will be moving material through the night in an area illuminated by three light towers.

Salisbury is due to receive the first 40,000 of what is estimated to be a total of 160,000 cubic yards of sand. The Newbury section of Plum Island is slated to receive the other 120,000.

While asking for the public's patience in putting up with the inconvenience, Harrington also warned people to stay a safe distance away from the machinery.

"We also caution the public not to interfere with the work in any way by curiosity-seeking too close to the areas of the beach where the sand will be dumped," he wrote in his report to the selectmen.

The 40,000 yards of dredge material that will begin to arrive soon is double the amount of the last significant infusion of sand on the beach, 20,000 yards that was spread by the state Department of Conservation and Recreation after the Patriots Day storm of April 2007.

Text Only | Photo Reprints

Port Pics
AP Video
Father Accused of Using Leash on 11 Year Old Obama Helps Break Ground on Black History Museum Raw Video: Dozens Dead in Argentina Train Crash Megaupload's Kim Dotcom Released on Bail Two Western Journalists Killed in Syria Wounded Vets Regain Some Camaraderie in Kitchen Man Accused of Repeatedly Running Over Lover Ga. Authorities Say 5 Dead in Spa Shooting Raw Video: Obama Belts Out Blues FDA: New Suppliers to Ease 2 Drug Shortages Doctor Details Cancer Drug Needs and Shortage Raw Video: New Orleans Revels in Mardi Gras 'Super PACs' Overtaking Campaigns' Fundraising Raw Video: Mardi Gras Underway in New Orleans Mild Weather Could Affect Syrup Production Ex-IMF's Strauss-Kahn Questioned on Prostitution Raw Video: Iran Sailors Saved From Burning Ship Firm Suing Apple in China Open to Talks